Saturday, December 8, 2007

This is a picture of a hallway on the first floor, it shows the installed gypsum board drywall and the screws before they are filled. On the right side we can see the joint where 2 pieces of vertical drywall meet (not horizontal like is recomended). There is no drywall tape or joint compound filled in at this point.
The manager of the construction showed me a room on the first floor that had all the electrical lines coming in from the entire building.
The wall on the right is a stucco finish and between the door there is a gap left -a joint to-be filled with caulk to allow for movement/expansion/contraction between two different materials

No comments: